Why this is relevant — Shielded cable assemblies share the same component shortage mitigation discipline this currency technology case demonstrated.
During mass production of currency-processing cable harnesses, specific branded components faced global shortages.
- Challenge
- Shortages of 3M cables and specific TE Connectivity connectors (e.g., 342101-1) threatened to extend lead times beyond the required 2-3 weeks.
- Solution
- Proactively sourced alternative high-quality components and proposed validated domestic substitutes with equivalent UL certifications to the customer's engineering team, negotiating acceptable alternatives.
- Result
- Maintained delivery schedules despite global component shortages, keeping the multi-PO program on track without line-down events.
- TE Connectivity part 342101-1
- 3M cables
- Standard lead time: 2-3 weeks
- UL certified alternatives