A US high-end boat manufacturer needed to move from design validation to physical prototypes for custom audio and harness systems.
- Challenge
- The customer needed prototypes quickly to validate the design before committing to mass production, but tooling development typically delays this process.
- Solution
- Structured a phased approach: a dedicated 3-4 week tooling development cycle, followed by prototype production, with free samples provided to the customer for final physical evaluation.
- Result
- Customer confidently placed the tooling PO, accelerating the transition from a 9-month evaluation phase to a confirmed prototype and pre-mass-production stage.
- 3-4 weeks tooling lead time
- free samples provided